Project Updates
Stay informed with the latest progress reports and site news from our ongoing infrastructure development in Plain City.
07/07/2026
Shift Utilities & Remove Asphalt
As early as July 7, 2026 work begins with utility relocation efforts. Asphalt will be removed along the entire route at the start of construction. Local traffic only allowed. All detours will be posted.
08/15/2026
Road Widening & Concrete Work
As early as mid-August 2026 primary road widening reconstruction will begin with curb and gutter work. Coordination with school will be underway shortly to accommodate safe routes for children.
09/2026
Paving & Striping
The route will be paved in approximately one week. Striping and signs to be placed immediately following.
10/2026
Expected Project Completion
Construction cleanup and final inspections marks the conclusion of the 3600 West infrastructure improvement.
Project Documentation
Access official project maps and public information files. Section still under development.