top of page

Project Updates

Stay informed with the latest progress reports and site news from our ongoing infrastructure development in Plain City.

07/07/2026
Shift Utilities & Remove Asphalt
07/20/2026
Road Widening & Concrete Work
08/14/2026
Paving & Striping

Work began July 7, 2026 with utility relocation efforts. Asphalt was removed along the entire route at the start of construction. Utility work continues Local traffic only allowed. All detours are posted.

Mid-July 2026, primary road widening reconstruction began with curb and gutter work. Coordination with Elementary school occurred on 7/30 to accommodate safe routes for children.

Paving operations will take place in 2 different stages. Paving for the first phase occurred on the northern half of the route on August 14 & 21. The second half of paving will happen as early as October 19, and should take roughly one week to complete. Crews will finish by painting lines and installing street signs right after paving.

09/14/2026
09/22/2026
10/30/2026
2200 N Intersection Closure
Curb & Gutter Installation
Expected Project Completion

Starting Monday, Sept. 14, the intersection of 3600 W and 2200 N is fully closed to all traffic for utility work involving deep trenches. For everyone’s safety, the closure is expected to last for up to three weeks.

Starting as early as Tuesday, Sept. 22, through Oct. 2, crews will be installing curb and gutter concrete work from 1975 N to 2200 N along 3600 W. This will require 24/7 driveway access restrictions for those residents as well as restricted street parking during working hours (7 am– 6 pm).

 

Curb and Gutter work along 1975 N will occur as early as Wednesday, Oct. 14 through Oct. 24 and will also require 24/7 driveway access restrictions and street parking during working hours. 

Construction cleanup and final inspections marks the conclusion of the 3600 West infrastructure improvement.

Safe Route to School

Due to ongoing construction on 3600 West, children will need to use an alternate route to ensure their safety. We have coordinated with Plain City Elementary to establish a designated safe path away from the work zone. Please review the flyer below for the updated pedestrian route.

Safety Reminder: Keep Children Away from the Work Zone

For everyone’s safety, please keep children and pets away from the construction area at all times. Heavy equipment, open trenches, and changing traffic patterns can create hazards that may not be obvious. Never allow children to play near cones, barricades, or machinery, and remind them to stay on sidewalks and use designated crossings only. Thank you for helping keep our community safe during construction.

Project Documentation

Access official project maps and public information files.  Section still under development.

bottom of page