Project Updates

Stay informed with the latest progress reports and site news from our ongoing infrastructure development in Plain City.

07/07/2026
Shift Utilities & Remove Asphalt

Work began July 7, 2026 with utility relocation efforts. Asphalt was removed along the entire route at the start of construction. Utility work continues Local traffic only allowed. All detours will be posted.

07/20/2026
Road Widening & Concrete Work

As early as mid-July 2026 primary road widening reconstruction will begin with curb and gutter work.  Coordination with Elementary school occurred on 7/30 to accommodate safe routes for children.

08/14/2026
Paving & Striping

Paving operations will take place in 2 different stages. Paving for the first phase will take place on the northern half of the route and is scheduled for August 14-15. The second half of paving will happen around mid-September and should take roughly one week to complete. Crews will finish by painting lines and installing street signs right after paving.

10/2026
Expected Project Completion

Construction cleanup and final inspections marks the conclusion of the 3600 West infrastructure improvement.

Safety Reminder: Keep Children Away from the Work Zone

For everyone’s safety, please keep children and pets away from the construction area at all times. Heavy equipment, open trenches, and changing traffic patterns can create hazards that may not be obvious. Never allow children to play near cones, barricades, or machinery, and remind them to stay on sidewalks and use designated crossings only. Thank you for helping keep our community safe during construction.